The UK's Laggan Tormore natural gas field is set to return almost a week earlier than originally expected from planned maintenance work, operator Total said in a REMIT message late Sunday.
Laggan Tormore, which feeds gas into the St. Fergus NSMP receiving terminal on Scotland's east coast, is now due to return from maintenance at 15:00 local time (1400 GMT) Friday.
The work, which begun on May 31, were originally set to last until the beginning of the June 29 gas day.
The full 11.5 million cu m/d capacity of the field will remain offline until the work has been completed.
Flows into the UK National Transmission System via St. Fergus NSMP were running at 10 million cu m/d Monday morning.